MASTIC ASPHALT | MCGM CWC WORK

Project info - MASTIC ASPHALT | MCGM CWC WORK

Project Scope: Scarifying existing surface laying asphalt macadam & laying mastic asphalt in various junction in western suburbs under MCGM (Sub Contract )

Total Area: 5.65 Lakhs Sq.Mtr

  • Client: Ramesh & Associates

  • The major scope of works:

  • 1. Excavation removal of surplus earth
    2. Foundation work
    3. Sub base in 3 layers
    4. WBM in 2 layers
    5. Asphalt Mecadam 75 mm thick
    6. Mastic Asphalt 40 mm thick